    Working with Eskom ( nightmare )

    I have a very good working relationship with the Municipality.

    Both the Munic and I understand that a COC cannot be issued until such time that live testing has been done on a new installation.
    They are very accomodating as far as this is concerned.

    So now we've completed the wiring in a small house in a village out of town serviced by Eskom.

    The client has been trying now for 3 months to get some action from Eskom to have a stubby installed.
    Eventually after 3 months she receives a quote from Eskom that expires in a weeks time.
    Before they are prepared to lay on a supply ( install a stubby ) they insist that she presents a COC for the installation.

    I explained to both her and Eskom that a valid COC cannot be issued without first doing the live testing and this
    cannot happen without the installation having a supply. Eskom wont budge and insist on a COC before they are willing to assist her.

    I have given this plenty thought and because the client was in tears after struggling for 3 months just to get someone's attention
    at Eskom and it is impossible to proceed, I issued a COC.

    Attached is a copy of the test report.

    Am I now a criminal ?
    If so, what should I have done ?

    How can one actually get it to sink in at Eskom that they are forcing us to issue invalid COC's ?

    Click image for larger version. 

Name:	Scan_20220707_173339.jpg 
Views:	391 
Size:	74.7 KB 
ID:	8583

  2. #2
    Platinum Member
    Join Date
    Jun 2017
    Location
    Port Elizabeth
    Posts
    1,443
    Thanks
    40
    Thanked 337 Times in 283 Posts
    It is unfortunately what they want - The reasoning is to try ensure that a legitimate contractor has been employed to do the installation and if something goes wrong Eskom say , Your contractor should have checked

  3. #3
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    2,274
    Thanks
    60
    Thanked 103 Times in 98 Posts
    Like the COC layout, there should be a document used specifically for new installs.

    This is common practise with councils, we have the same issue, nothing is going to change.

    Like everything else, just smile and hand in a document, in most cases the person who receives the document will not understand the information written on it and it will be gone into file 13 within a month.

    In the Truman bubble, there would be a page used for the new application, with a sketch of the property layout indicating the meter location, the insulation resistance readings, type of cabling used and the size, current rating of the supply required and a few other details. This information would be attached to original COC , with the test results once the supply is installed.

    At least its not a 4 page document anymore and it can be filled out in PDF, so you can make a pile of them with all the "common" test results.

Similar Threads

  1. What A Nightmare
    By SparkyScott in forum Electrical Contracting Industry Forum
    Replies: 11
    Last Post: 19-Jul-11, 12:05 AM
  2. CoC Nightmare
    By daveob in forum Electrical Contracting Industry Forum
    Replies: 2
    Last Post: 10-Aug-10, 11:00 PM
  3. Then NCA nightmare!
    By Xander in forum National Credit Act Forum
    Replies: 23
    Last Post: 31-May-07, 07:22 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •