    COC for new house supply cable

    Hi guys

    I've quoting on a job that involves installing a new 16mm airdac from boundary wall into house main DB.
    Municipality taking down overhead line as home owners want the line underground.
    Will a COC need to be issued for this?
    Or is it optional depending on owners?

    Thanks

  2. #2
    Platinum Member
    Join Date
    Jun 2017
    Location
    Port Elizabeth
    Posts
    1,443
    Thanks
    40
    Thanked 337 Times in 283 Posts
    In theory it is not optional - Is a requirement under the OHSA

    The municipality will more than likely want a COC before connecting the underground cable - All you have to do is a coc from meter box to the top of the main switch.

    Again in theory a COC must be issued for any electrical installation work. The definition for Electrical installation work is " from point of control to point of consumption"
    Since point of control is the main switch in the house not the meter box you should not have to issue a coc - You will go blue in the face having this discussion with Municipality , will be easier to just write it out.

    I have done a good job of contradicting myself in one paragraph

  3. #3
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,945
    Thanks
    582
    Thanked 938 Times in 759 Posts
    As per GCE. I've argued till I'm blue in the face with the municipality that a CoC for a supply cable is an invalid document but they won't connect a supply without it. As GCE suggested, we issue a CoC just for the supply cable and exclude everything else (ie the entire installation).
    _______________________________________________

    _______________________________________________

Similar Threads

  1. Cable supply for a building
    By ians in forum Electrical Contracting Industry Forum
    Replies: 4
    Last Post: 20-Aug-19, 09:13 AM
  2. [Question] Relocation of the supply cable.
    By Ishmaelmo in forum Electrical Contracting Industry Forum
    Replies: 7
    Last Post: 15-Nov-18, 06:47 AM
  3. supply cable
    By murdock in forum Electrical Contracting Industry Forum
    Replies: 7
    Last Post: 20-Apr-12, 12:08 PM
  4. [Article] Exe cable glands for braided cable
    By Master Electrician in forum Electrical Contracting Industry Forum
    Replies: 0
    Last Post: 26-Aug-10, 02:47 PM
  5. [Question] Supply
    By Dusty in forum Electrical Contracting Industry Forum
    Replies: 3
    Last Post: 14-Apr-10, 10:36 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •