    it is a single phase installation using the main contacts for the supply and the n/c contact for the generator...so there is no way the mains and generator can be on at the same time...the problem is the n/c contact while the generator is running the 30 amps are being drawn through the aux n/c contact which is not rated for 30 amps...but i say it again it doesnt help making a whole lot of rules and not policing them...i need that banging my head on the wall smilie...please add it dave.

  2. #2
    Site Caretaker Dave A's Avatar
    Join Date
    May 2006
    Location
    Durban, South Africa
    Posts
    22,789
    Thanks
    3,331
    Thanked 2,694 Times in 2,271 Posts
    Blog Entries
    12
    Aaah. Gotcha.

    I'm amazed I never added the banghead smilie... Maybe it's time to add a new batch.

  3. #3
    Email problem
    Join Date
    Oct 2012
    Location
    DURBAN
    Posts
    23
    Thanks
    0
    Thanked 3 Times in 2 Posts
    SANS 10142-1:2012
    Edition 1.8
    (As amended Jan. 2003, Dec. 2003, 2008 and 2012)
    Annex S (informative) Has Examples of emergency power installation configuration

  4. #4
    Suspended
    Join Date
    Oct 2007
    Posts
    2,346
    Thanks
    0
    Thanked 254 Times in 209 Posts
    what you have to consider...who is gona go down when you install the incorrect equipment (if we ever actually get the policing of the industry going) i can assure you not the wholesaler...because he doesnt sign the COC to verify all the goods he sold you are sabs approved.

    this industry has too many loop holes and too few skilled enough people and not enough money in the budget to waste on trival things like the electrical industry...not enough people are killed from electrical problems to warrent money being wasted on policing the industry...or that how it looks to me looking from the outside.

    just think if they got smart and thought like the road traffic department thinks...they could make billions...train up people and send them out to bussiness and homes and fine people if their electrical installtion was not up to standard or if they cant produce a COC...if you dont wear a seat belt you get a fine...even though you are not endangering anyone elses lives you still get a huge fine....its aj oke but it must be one of the biggest money making rackets in SA...after hidden camers for speeding...cameras in the bush must actually print money...i dont know about making the road any safer...just bigger bonuses for the fat cats.

    just think they could make you put a code on you meter box which would verify that your house has a COC ...which the meter reader scans and then they could check it on the system and if your COC had expired or you dont have one the computer log it and another person in a different department would be asigned to go and investigate...creating employment....making electrical installtions safer and i could become a billionare for coming up with the idea...and then add appliance testing like hey do in the UK and create even more employment...create more opitunities for conferences to waste more of our tax money...create more task teams to waste even more of our tax money...the only catch is you need skilled people...not like washing street signs...the people would actually have to be able to switch on a pc.

  5. #5
    Suspended
    Join Date
    Oct 2007
    Posts
    2,346
    Thanks
    0
    Thanked 254 Times in 209 Posts
    Quote Originally Posted by Kevin Stubbs View Post
    When connecting a generator to the electrical board of my house ,do I have to install cross over switches on the neutral and earth as well
    by the question i can only assume you are not qualified to do the installation but if you plan on doing anyway....do you have a 3 phase supply or single phase supply...are you installing a automatic changeover system or manual?
    are you feeding the entire electrical installation with the generator or only part....have you made provision for only partial if using a small generator...have you installed an earth spike...are plugs being fed from the generator on earth leakage...have you fitted barriers in the DB if only feeding part of the DB...have you clearly labelled the DB indicating which part of the DB will be fed by the generator...do you have a main switch in the DB if only part of the DB is supplied by the generator to isolate that part of the installation in case of accident leakage...have you done a loop impedance test and earth leakage test to verify if the earth leakage will trip in case of a fault while running on generator power...etc etc etc.

  6. #6
    New Member
    Join Date
    Jan 2008
    Posts
    3
    Thanks
    0
    Thanked 0 Times in 0 Posts
    Quote Originally Posted by murdock View Post
    by the question i can only assume you are not qualified to do the installation but if you plan on doing anyway....do you have a 3 phase supply or single phase supply...are you installing a automatic changeover system or manual?
    are you feeding the entire electrical installation with the generator or only part....have you made provision for only partial if using a small generator...have you installed an earth spike...are plugs being fed from the generator on earth leakage...have you fitted barriers in the DB if only feeding part of the DB...have you clearly labelled the DB indicating which part of the DB will be fed by the generator...do you have a main switch in the DB if only part of the DB is supplied by the generator to isolate that part of the installation in case of accident leakage...have you done a loop impedance test and earth leakage test to verify if the earth leakage will trip in case of a fault while running on generator power...etc etc etc.
    This goes back a long way, Thanks for your reply.
    The supply is single Phaze. I would feed the entire electrical instalation. Manual change over. The DB has earth leakage and it does work on the generator.
    My main question is ,does the crossover/change over switch have to include the neutral and earth, I have had mixed answers on that point from people in the profession.
    Some say I dont have to switch the neutral and earth as well, some say I have to switch the neutral but dont have to do the earth.
    Kevin

  7. #7
    Suspended
    Join Date
    Oct 2007
    Posts
    2,346
    Thanks
    0
    Thanked 254 Times in 209 Posts
    if anyone can get hold of the electricity department bylaws in durban...please let me know...i have left numerous messages for sherwyn from customer services but he doesnt return his calls...and when you speak to customers services help line nobody has aclue what i am talking about...they dont know what methods and standards...and there fore cannot put me through to someone in that department...sad...and we wonder why our industry is in such a "shocking" state.

    after making that statement it cant be that bad...how often do you hear of buildings burning down and people getting electricuted...not that often...maybe our standards are just too high.

  8. #8
    Junior Member
    Join Date
    May 2012
    Location
    south africa
    Posts
    15
    Thanks
    0
    Thanked 0 Times in 0 Posts
    the municipality i work for requires the consumers to inform them if they intend to use a generator during a planned power outage! they also state that it must be installed by a qualified electrician! we have lost a contractor a few years back due a generator backfeeding on a 11kV line he was working on! i suppose every municipality might have different criteria but the basics should be the same! get a qualified person to do the installation and get a criteria from your municipality. if you dont come right at the bottom go to the top! phone the electrical engineer or his assistant!

  9. #9
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,946
    Thanks
    583
    Thanked 938 Times in 759 Posts
    Quote Originally Posted by inusjvr View Post
    the municipality i work for requires the consumers to inform them if they intend to use a generator during a planned power outage! they also state that it must be installed by a qualified electrician! we have lost a contractor a few years back due a generator backfeeding on a 11kV line he was working on!
    I don't think there's enough awareness about how dangerous back-up generators are, not only for the user of the installation but also for the guys working on the upstream networks. I'm actually surprised there hasn't been a lot more fatalities.

    I think acombination of factors are to blame. Retailers and wholesalers alike are selling site generators as a domestic back-up solution to the end users. Many of these generators are completely unsuitable as domestic premises backup because of the way their windings are configured and they're often temporarily installed using a lead with a plug top on each side with little or no regard for interlocked isolation of the main Eskom supply or safe local earthing arrangements.

    Many qualified electricians are sadly lacking in this area as well, I've seen many installations that were done 'professionally' but have been unsafe or non-compliant.
    _______________________________________________

    _______________________________________________

  10. #10
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,946
    Thanks
    583
    Thanked 938 Times in 759 Posts
    You must switch both the live and neutral. No switching of the earth, earth bonds must be permanant connections.

    If you're not qualified I would urge you to seek professional help with this. Firstly mistakes could kill someone (most likely the next electrician on site) and secondly mistakes can be expensive when it comes to generator damage.

  11. Thanks given for this post:

    Dave A (10-Feb-10)

Page 2 of 4 FirstFirst 1234 LastLast

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •