GCE is referring to the Electrical Contractor registration details section which has been struck through with N/A.
GCE is correct. This section must be completed (unless issued by the owner who happens to be a registered Responsible Person) as the Electrical Contractor registration is a different registration to the Responsible Person registration (albeit both registrations being with DoL which I suppose may be confusing to the general public).
GCE is correct. This section must be completed (unless issued by the owner who happens to be a registered Responsible Person) as the Electrical Contractor registration is a different registration to the Responsible Person registration (albeit both registrations being with DoL which I suppose may be confusing to the general public).