I also noted that the COC has changed with regards to inspections for electrical installation which have more than 5 installations on one supply.
Testing an installation with more than 5 installations
Collapse
X
-
5 installations? You mean subdbs? or like houses on a property, flats? Subdivided house? The regs says that each DB shall have its own test report BUT only one 'Certificate of Compliance' per municipal/eskom supply. hope that helps.Im with stupid --> ooo wheres he gone??
-
SECTION 5 – RESPONSIBILITY
NOTE For existing installations, complete only 5.4. For new/altered/temporary installations, if no signature appears in 5.1 to 5.3, the signatory of 5.4
takes responsibility. Where there are five or more installations on the same supply, a competent person signs 5.5.
5.5 COMPLIANCE OF INSTALLATION FROM COMMENCEMENT TO COMMISSIONING. I................................................. ........................ being the person
responsible to ensure that the electrical installation, particulars of which are described in section 3 of this form and which is one of five or more
installations on the same supply, CERTIFY that the installation was done in accordance with SANS 10142-1.Comments are based on opinion...not always facts....that's why people use an alias.Comment