    New pastel user - I can assign customer invoices to project jobs but when I enter in a supplier invoice the project column is uneditable......how do I assign costs to projects?
  • Neville Bailey
    Diamond Member

    • Nov 2010
    • 2786

    #2
    Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

    The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
    Neville Bailey - Sage Pastel Accounting Consultant
    www.accountingsoftwaresupport.co.za
    neville@accountingsoftwaresupport.co.za
    IronTree Online Solutions

    "Give every person more in use value than you take from them in cash value."
    WALLACE WATTLES (1860-1911)

    Comment

    • TravisZA
      Bronze Member

      • Sep 2014
      • 108

      #3
      Originally posted by Neville Bailey
      Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

      The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
      Thanks Neville. Problem solved.

      Comment

      • Sabie
        Email problem
        • Mar 2021
        • 3

        #4
        Originally posted by Neville Bailey
        Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

        The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
        When allocating payments in Cashbook Payment to such invoices - Do we also select "Project" on Cashbook Payment?

        Comment

        • Neville Bailey
          Diamond Member

          • Nov 2010
          • 2786

          #5
          Originally posted by Sabie
          When allocating payments in Cashbook Payment to such invoices - Do we also select "Project" on Cashbook Payment?
          Not necessary, as you would have already assigned the invoice to a project.
          Neville Bailey - Sage Pastel Accounting Consultant
          www.accountingsoftwaresupport.co.za
          neville@accountingsoftwaresupport.co.za
          IronTree Online Solutions

          "Give every person more in use value than you take from them in cash value."
          WALLACE WATTLES (1860-1911)

          Comment

          Working...