The building is a double story, fortunately I installed 2 x 32 mm PVC conduit as spares, when I rewired the building, they run from the roof to the room
Isetech Today, 05:48 PMWe started with the 12 kw 3 phase inverter, battery, AC and DC controls today.
I laid out all the stuff, mounted the inverter, went through
The way we would normally do it, screw nuts onto the threaded rod and fit a new cable tray below the power tray.
One of the factories I work,
I didnt get back to this site today, ended up north of the river river. I have another challenge, where to install my 3 lithium batteries, in a complex.
Isetech Today, 04:53 PM
Inverter and battery install
Then we come to the lithium batteries, I thought I would just flip it to the architect, who got the roof assessment done., but they came back and said
Isetech Today, 06:04 PM