The sketches are complete, points identified and visual inspection complete. By the way this is actually being done on a site that we are busy working.
Isetech Today, 05:37 PMDear Community,
Assuming the following scenario:
1 inventory item set up in Pastel, with:
- Category field set as 000
Before I look at the COC document, I create a sketch of the property and as I do the visual inspection, then mark all the electrical points and make
Isetech Today, 02:30 PMThe idea of this thread is to guide people in the right direction, with regards to COC/test reports.
Scope of work:
1/ Rewire
How to complete a COC/test report
Now it is time to start with the COC document.
Isetech Today, 05:46 PMAnnexure 1 - If you dont know how to fill out this first page, I would suggest you maybe