Please see the process for residential/commercial customer application to install SSEG below:
Please also note that the customer will need to obtain approval from the Municipality prior to any SSEG installation. I have outlined the application process for your ease of reference below:
Submit the following documentation to (residential.generation@durban.gov.za or Commercial.Generation@durban.gov.za) depending on the application made and copy sanjeeth.sewchurran@durban.gov.za on the email.
1. Completed application form (residential and commercial application forms attached)
2. NRS 097 inverter certificate
3. Operating Philosophy if you have batteries/supercapacitors to be installed
4. Equipment data sheets
5. Detailed Single Line Diagram
6. PV/generation production simulation report
Once the application is assessed and approval is given, construction may commence. On completion of construction and commissioning, the following is required:
1. COC
2. Completed commissioning report (attached above)
3. Pr Eng/Pr Tech sign off letter for the installation
4. As built drawing if any changes were made to SLD submitted
5. View access to the PV generation portal
Once the above is received, we will set up a site inspection and if all is in order then we will issue with a letter.
However, take note that there could be additional requirements such as a Grid Impact Study that will be needed to be carried out by the applicant depending on the size of the proposed generation system.