    People seem to have tons cash to throw at this industry at the moment, you might say maybe not, all you have to do is look at the supply and demand. If a container lands today, the 500 units in the container are already sold and paid for, the container arriving in 2 days time, the contents are already sold and paid for.

    Smart people have made a lot of money, dont let anyone bullshyte you that the margins are small, it doesnt matter when you turning over R10 M a week and already have money in the bank for shipments due to arrive for the next month or two.

    R6000 profit on A R30 k battery is not a "small margin" as someone pointed out to me the other day. 2.5 % margin would be regarded as a small margin

    It got me thinking if everyone is rushing and blows R150 + on a solar system, the energy crisis will be over sooner then later, unless you have a couple bar to buy up stock and make tons of cash, while people a silly spending, wouldnt it be smarter to just be patient. We still havent had load shedding, and it doesnt seem like we will be affected any time soon.

  2. #12
    Platinum Member Derlyn's Avatar
    Join Date
    Mar 2019
    Location
    East london
    Posts
    1,484
    Thanks
    104
    Thanked 141 Times in 134 Posts
    Quote Originally Posted by Isetech View Post

    A backup off grid inverter/UPS which has solar panels and connected to the grid, but is not bi directional, so it cant feedback into the grid?

    I tend to disagree. It is never connected to the grid.

  3. #13
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    Quote Originally Posted by Derlyn View Post
    I tend to disagree. It is never connected to the grid.

    How does that sound?

    *EDIT* A backup off grid inverter/UPS which has solar panels and connected to the DB, but is not bi directional, so it cant feedback into the grid?

  4. #14
    Platinum Member Derlyn's Avatar
    Join Date
    Mar 2019
    Location
    East london
    Posts
    1,484
    Thanks
    104
    Thanked 141 Times in 134 Posts
    Cool. Because it's connected to the DB, doesn't mean it's connected to the grid. 👍👍

  5. #15
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    What is the DB connected to?

    Quote Originally Posted by Derlyn View Post
    Cool. Because it's connected to the DB, doesn't mean it's connected to the grid. 

  6. #16
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    Now that we are growing faster than expected, so the registration process has become a populer topic. We are no longer sticking to our reguler customers, so the registration process will become part of the package to CYA.

    A few things to consider as we live and learn

    Nobody has a clue what the peanlty will be yet, which makes it rather interesting, if the fine is going to be R5000 for example big deal, if you have had your sytem for 5 years already, R5k is a splash in the ocean, concidering all the savings.


    What sort of costs are involved in registering a system:

    1/ The application fee, which by the way is not just the cost of the meter, the longer you delay your registration the harder it will become to register.

    2/ The cost for the engineer from the desgn process to the hand over of the commisioned system.

    3/ The monthly fee charged by the council.

    The big question os Ethekwini for example, ready for SSEG applications?

    When will Ethekwini be ready for SSEG applications?

    https://www.durban.gov.za/storage/Do...02022-2023.pdf

    Note on page 8:

    The Municipality will facilitate an application process to interconnect SSEG systems.We have designed an application process to collect and evaluate relevant information pertaining to the connection ofSSEG systems to the grid. All SSEG systems must gain approval from the Municipality in advance of installation, andadhere to relevant technical guidelines to ensure systems are safely wired and connected.Separate SSEG tariffshave been developed for residential, business and industrial SSEG customers. Tariffs are not yet active and currentlyundergoing the approval process.

  7. #17
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    Step 3
    The purpose of this form is to formally request for the connection of your SSEG system to the grid, bi-directional metering and a tariff change to the embedded generation tariff structure (Scale 15).Three requests are captured via this application. The capturing of this form onto our system will generate a unique reference number, i.e. an “E” number. This will be used to track your application throughout the process. Upon capturing your form, this reference number will be forwarded to you.

  8. #18
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    The email addressd to deal with SSEG registrations.

    residentialgeneration@elec.durban.gov.za

  9. #19
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    No a domestic meter is not read every month.

    Read Page 43

    How often is my meter read?Residential meters are read every three month and Businesses are read every month

  10. #20
    Platinum Member
    Join Date
    Mar 2022
    Location
    South Africa
    Posts
    1,985
    Thanks
    55
    Thanked 93 Times in 89 Posts
    I am starting to think it might not be a bad idea to get my customers SSEG registered sooner than later.

    The application fee is made up of the repalcement meter cost and all the other costs to ensure your grid can handle the load.

    If you get in early, you shouldnt be hammered with any upgrade costs if your grid cant handle the additional power feeding back into the grid

Page 2 of 2 FirstFirst 12

Similar Threads

  1. max Uoc allowed on residential off grid (non embedded) system
    By Frans400 in forum Electrical Contracting Industry Forum
    Replies: 8
    Last Post: 25-Sep-20, 08:04 AM
  2. Introducing 'The next generation Zuma'
    By wynn in forum South African Politics Forum
    Replies: 4
    Last Post: 11-Nov-14, 01:30 PM
  3. How to remove Skype embedded numbers?
    By Neville Bailey in forum Technology Forum
    Replies: 3
    Last Post: 17-May-12, 09:59 PM
  4. [Question] new generation
    By murdock in forum South African Politics Forum
    Replies: 15
    Last Post: 02-Aug-11, 10:09 PM
  5. Previous posts embedded
    By sterne.law@gmail.com in forum Administrative issues
    Replies: 12
    Last Post: 15-Feb-10, 08:16 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.