I am required to replace a worn 16 mm cable feeding from the main munc. supply to the house connection, after paying the elect. dept and making an appointment for the elect inspector to switch off to do the work ,he told me that before switching on the supply, he will need a copy of a COC.
My question is how do you supply a COC immediately after the connection is done, he only wants the COC for the cable joint?, under normal circumstances we do the whole premises. also read elsewhere in the thread that only a full COC is to be supplied.
I have to send it the the ECB to get a DOL copy, and this will take some time?