    Question Alterations to Existing Supply

    Hi Guys
    I am wondering if anybody can shed some light on a on a problem that I have. I am an industrial electrician and do not renovate domestic dwellings however I have been asked to do some alterations to the existing supply of an old flat, mainly to remove the old existing Dist.Board it is at present a fused isolator and fuses, about 60 years old and does not have an E.L.U. installed. The premises have been rewired in the past as there is PVC wiring and not the old VIR wiring, the supply authority (Municipality) have installed a prepaid unit which is understandably sealed. Now my problem is the sealed prepaid unit which has to be moved and reinstalled. Who do I approach and obtain permission to do this alteration? I am a registered Installation electrician and not a registered electrical contractor.
    Thanks

    Mikilianis

  2. #2
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,923
    Thanks
    576
    Thanked 934 Times in 755 Posts
    I'm also not very well up on the domestic side of things but the last time I relocated an energy dispenser (a few years ago) I contacted the council to disconnect and they removed the entire front of the ED. I then relocated the back of the ED and installed the new cabling and when I was finished they came and refitted the front again.
    _______________________________________________

    _______________________________________________

  3. Thanks given for this post:

    mikilianis (29-Oct-16)

  4. #3
    Full Member MullerR's Avatar
    Join Date
    Jan 2016
    Location
    Lady Grey
    Posts
    44
    Thanks
    3
    Thanked 6 Times in 5 Posts
    The supply authority is responsible for the movement of the meter. Best way is to go to the supply authority and apply for the movement of the meter or get the info from them on how to go forward with it.

  5. Thanks given for this post:

    mikilianis (29-Oct-16)

  6. #4
    Email problem
    Join Date
    Sep 2010
    Location
    cape town
    Posts
    308
    Thanks
    3
    Thanked 43 Times in 37 Posts
    contact the depot in mowbray. you will have to submit an application to disconnect , then reconnect and submit a CoC. i dont think you can do it without being registered as an electrical contractor.

  7. Thanks given for this post:

    mikilianis (31-Oct-16)

Similar Threads

  1. [Question] Registering an existing business for tax
    By Jacky in forum Tax Forum
    Replies: 5
    Last Post: 22-Sep-14, 02:29 PM
  2. Purchasing an existing franchise
    By Dastan Kieton in forum Entrepreneurship and Business Management Forum
    Replies: 0
    Last Post: 23-Oct-12, 12:05 PM
  3. [Question] Existing vs New/altered /temp installation?
    By siphom_3 in forum Electrical Contracting Industry Forum
    Replies: 2
    Last Post: 21-Jun-11, 03:44 PM
  4. [Article] Funding for existing businesses
    By QUINN in forum Business Finance Forum
    Replies: 0
    Last Post: 11-May-09, 05:22 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •