    Posting supplier invoices to projects in Pastel

    New pastel user - I can assign customer invoices to project jobs but when I enter in a supplier invoice the project column is uneditable......how do I assign costs to projects?

  2. #2
    Diamond Member Neville Bailey's Avatar
    Join Date
    Nov 2010
    Location
    Westville, Durban
    Posts
    2,760
    Thanks
    44
    Thanked 451 Times in 396 Posts
    Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

    The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
    Neville Bailey - Sage Pastel Accounting Consultant
    www.accountingsoftwaresupport.co.za
    neville@accountingsoftwaresupport.co.za
    IronTree Online Solutions

    "Give every person more in use value than you take from them in cash value."
    WALLACE WATTLES (1860-1911)

  3. #3
    Bronze Member
    Join Date
    Sep 2014
    Location
    South Africa
    Posts
    108
    Thanks
    3
    Thanked 1 Time in 1 Post
    Quote Originally Posted by Neville Bailey View Post
    Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

    The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
    Thanks Neville. Problem solved.

  4. #4
    New Member
    Join Date
    Mar 2021
    Location
    Johannesburg
    Posts
    3
    Thanks
    0
    Thanked 0 Times in 0 Posts
    Quote Originally Posted by Neville Bailey View Post
    Have a look at your settings in Setup...Inventory...Integration/Groups tab - you have more than likely set it up so that Project costs get allocated at the time of sale (Cost of Sales), not at the time of purchase.

    The above setting makes sense if you are using the integrated stock system, in which inventory purchases are allocated to the inventory control account (asset account) and not to an expense account, and the expense is only accounted for at the time of sale, as Cost of Sales.
    When allocating payments in Cashbook Payment to such invoices - Do we also select "Project" on Cashbook Payment?

  5. #5
    Diamond Member Neville Bailey's Avatar
    Join Date
    Nov 2010
    Location
    Westville, Durban
    Posts
    2,760
    Thanks
    44
    Thanked 451 Times in 396 Posts
    Quote Originally Posted by Sabie View Post
    When allocating payments in Cashbook Payment to such invoices - Do we also select "Project" on Cashbook Payment?
    Not necessary, as you would have already assigned the invoice to a project.
    Neville Bailey - Sage Pastel Accounting Consultant
    www.accountingsoftwaresupport.co.za
    neville@accountingsoftwaresupport.co.za
    IronTree Online Solutions

    "Give every person more in use value than you take from them in cash value."
    WALLACE WATTLES (1860-1911)

Similar Threads

  1. [Question] Pastel Xpress (Start-up) - How to correct SUPPLIER invoices
    By Tato in forum Accounting Forum
    Replies: 5
    Last Post: 25-May-15, 12:23 PM
  2. How does Pastel link a Supplier Return to a Supplier Invoice?
    By Leigh Peiser in forum Accounting Forum
    Replies: 0
    Last Post: 27-May-14, 02:03 PM
  3. Pastel Xpress 12 Projects
    By xpressnewbie in forum Accounting Forum
    Replies: 0
    Last Post: 28-Mar-14, 06:43 AM
  4. [Question] Force Projects in Pastel Express Version 12
    By DesBarata in forum Accounting Forum
    Replies: 2
    Last Post: 14-Jan-14, 07:33 AM
  5. [Question] Supplier Invoices and vat
    By Jforssman in forum Accounting Forum
    Replies: 7
    Last Post: 23-Nov-12, 08:07 AM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •