    Testing an installation with more than 5 installations

    I also noted that the COC has changed with regards to inspections for electrical installation which have more than 5 installations on one supply.

  2. #2
    Full Member
    Join Date
    Aug 2010
    Location
    Pietermaritzburg KZN
    Posts
    32
    Thanks
    9
    Thanked 0 Times in 0 Posts
    Quote Originally Posted by ians View Post
    I also noted that the COC has changed with regards to inspections for electrical installation which have more than 5 installations on one supply.
    5 installations? You mean subdbs? or like houses on a property, flats? Subdivided house? The regs says that each DB shall have its own test report BUT only one 'Certificate of Compliance' per municipal/eskom supply. hope that helps.

  3. #3
    Diamond Member
    Join Date
    Apr 2010
    Location
    planet earth
    Posts
    3,943
    Thanks
    153
    Thanked 317 Times in 287 Posts
    SECTION 5 – RESPONSIBILITY
    NOTE For existing installations, complete only 5.4. For new/altered/temporary installations, if no signature appears in 5.1 to 5.3, the signatory of 5.4
    takes responsibility. Where there are five or more installations on the same supply, a competent person signs 5.5.




    5.5 COMPLIANCE OF INSTALLATION FROM COMMENCEMENT TO COMMISSIONING. I................................................. ........................ being the person
    responsible to ensure that the electrical installation, particulars of which are described in section 3 of this form and which is one of five or more
    installations on the same supply, CERTIFY that the installation was done in accordance with SANS 10142-1.

Similar Threads

  1. questions asked about electrical installations and problems
    By murdock in forum Electrical Contracting Industry Forum
    Replies: 10
    Last Post: 20-Nov-17, 03:20 PM
  2. Stand alone Solar/Pv installations
    By CollenD in forum Electrical Contracting Industry Forum
    Replies: 19
    Last Post: 13-Jun-12, 02:21 PM
  3. CoC requirements for Solar Water Heating installations
    By Carbonic in forum Electrical Contracting Industry Forum
    Replies: 15
    Last Post: 07-Sep-10, 08:59 AM
  4. electrical installations
    By murdock in forum Electrical Contracting Industry Forum
    Replies: 10
    Last Post: 15-Jun-09, 04:21 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •