    Machine Panel COC

    Does anyone know what type of certificate should be issued with a panel build which will be used on a machine upgrade - is it certificate of compliance or certificate of conformity.

    Would the certificate of compliance be issued fro the supply connection to the panel bearing in mind that the panel will comprise of PLC, Inverter drives, power supply and relay etc.

    Whatever type of certificate that needs to be issued, I can only think of the normal type of information / tests eg supply voltage, neutral to earth voltage, earth resistance and checks to confirm that the cabling is up to required standards.

    What am I missing here?

  2. #2
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,923
    Thanks
    576
    Thanked 934 Times in 755 Posts
    The electrical certificate of compliance only covers the fixed building installation up to and including the isolator switch or the supply connection. It can't be issued for the control panel of a machine or even the supply cable going to it. The electrical company that installed the supply up to the connection point would have (should have) issued the certificate. If the supply was already existing then it would be covered by a previous COC.
    _______________________________________________

    _______________________________________________

  3. #3
    New Member
    Join Date
    Aug 2011
    Location
    Durban
    Posts
    2
    Thanks
    0
    Thanked 0 Times in 0 Posts
    The COC needs to be issued for all and any changes to an installation. If this was a residential installation and a further socket outlet was installed then a COC would have to be issued for that installed socket outlet.

    The same applies here. I will be making a change to the installation so therefore I will need to issue a COC. Furthermore the customer is insisting on one.

    I know that Certificates of Conformity can be issued for a panel but I do not know what requirements are required for this procedure and who is authorized to issue such certificate

  4. #4
    Diamond Member AndyD's Avatar
    Join Date
    Jan 2010
    Location
    Cape Town
    Posts
    4,923
    Thanks
    576
    Thanked 934 Times in 755 Posts
    Quote Originally Posted by Machine Elec View Post
    The COC needs to be issued for all and any changes to an installation.
    How are you altering the installation? Did you install the supply to the machine from the DB?
    _______________________________________________

    _______________________________________________

Similar Threads

  1. [Question] Softserv ice cream machine
    By AmithS in forum General Business Forum
    Replies: 4
    Last Post: 13-Sep-10, 08:45 PM
  2. Site transfer to new hosting machine.
    By Dave A in forum News Archive
    Replies: 1
    Last Post: 04-Jul-07, 04:53 PM

Did you like this article? Share it with your favourite social network.

Did you like this article? Share it with your favourite social network.

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •